- "YongKang Waset to Energy (incineration) Plant, Tainan County," transfer to the CPC Corporation
- "YongKang Waset to Energy (incineration) Plant, Tainan County" Project kickoff meeting.
- Plant inspection and audit was conducted by foreign technicians from a Austrian company named ENVIRGY.
- Completion of the first control point (the DCS control logic diagram was approved)
- Company registered. EPA’s equipment delivered.
- Completion of the temporary storage facility adjacent to the Plant's construction sites and finished moving the equipments and materials to the storage facility as ordered by the Court.
- Siemens AG, turbine-generator's foreign service consultant arrived at site, conducted the technical guidance of the equipment installation. YongKang and training preparation were conducted.
- Completion of phase one. Following the guidance of the Siemens turbine-generator’s consultant, the turbine generator was successfully installed.
- The completion of stack painting.
- A large garbage truck was sent by the Environmental Protection Bureau of Tainan County to conduct field measurement and contour of traffic route within the Plant.
- The completion of the second control point (the main facility and mechanical/electrical equipment is completed and received inspection certificate for pressure vessel and refuse crane)
- YongKang incinerator construction completed transmission of 161KV power from the Tai Power.
- Flue gases treatment (IDF) systems installed, foreign technicians arrived for IDF testing and IDF operation training.
- Stand alone testing were conducted for waste crane.
- Begin stand alone testing for the Plant’s air compressor supply system.
- Stand-alone testing of emergency diesel generator started
- Waste crane stand-alone testing was successfully completed, prepare to submit test reports
- No. 2 steam boiler to begin the roast and boil operation.
- No. 1 steam boiler to begin the roast and boil operation.
- Completion of Loadometer system testing and the personnel education and training.
- Tainan County Environmental Protection Agency’s garbage trucks were in the Plant for practicing garbage dumping and correct routing
- YongKang City, Tainan County Cleanup Team starting to transport garbage to the plant and dumping the waste into the storage pit
- County Magistrate Mr. Su Huanzhi came to the construction site for project status and briefing.
- Working with CTCI Corporation, the emission monitoring system testing was completed on-site.
- Scheduled for operation starts at 11 o'clock at this day. Plant testing was conducted.
- Chairman of CPC along with the Director of EPA, Mr. Su Huanzhi, County Magistrate and other elected local officials at all levels attend the Plant Ignition Ceremony.
- Completion of single unit testing.
- Completion of the third control point (turbine generator was successfully integrated with the Taiwan Power Company)
- Completion of trial run (end-to-end testing).
- Completion of functional testing (waste volume test).
- Completion of the entire YongKang incinerator plant functional testing.
- Improved the building metal plate.
- Inspection completed (low calorific waste processing diesel volume was re-verified)
- 1st round of acceptance test completed.
- Imperfection The deficiencies improvement completed (duration 30 days)
- Completion of 1st acceptance test improvement review.
- 2nd round of acceptance test completed.
- Formal acceptance on the deficiencies improvement completion (duration 30 days)
- Completion of 2nd formal acceptance test improvement review.
- EPA approved acceptance and project completion date.
- CPC hand over the plant to Tainan County Government.