Construction Timeline

  • 26-09-2003
    "YongKang Waset to Energy (incineration) Plant, Tainan County," transfer to the CPC Corporation
  • 21-10-2003 ~ 24-10-2003
    "YongKang Waset to Energy (incineration) Plant, Tainan County" Project kickoff meeting.
  • 12-03-2004
    Plant inspection and audit was conducted by foreign technicians from a Austrian company named ENVIRGY.
  • 08-04-2004
    Completion of the first control point (the DCS control logic diagram was approved)
  • 16-04-2004
    Company registered. EPA’s equipment delivered.
  • 16-08-2004
    Completion of the temporary storage facility adjacent to the Plant's construction sites and finished moving the equipments and materials to the storage facility as ordered by the Court.
  • 31-05-2005
    Siemens AG, turbine-generator's foreign service consultant arrived at site, conducted the technical guidance of the equipment installation. YongKang and training preparation were conducted.
  • 13-06-2005
    Completion of phase one. Following the guidance of the Siemens turbine-generator’s consultant, the turbine generator was successfully installed.
  • 08-08-2005
    The completion of stack painting.
  • 11-08-2005
    A large garbage truck was sent by the Environmental Protection Bureau of Tainan County to conduct field measurement and contour of traffic route within the Plant.
  • 21-10-2005
    The completion of the second control point (the main facility and mechanical/electrical equipment is completed and received inspection certificate for pressure vessel and refuse crane)
  • 18-12-2005
    YongKang incinerator construction completed transmission of 161KV power from the Tai Power.
  • 26-01-2006
    Flue gases treatment (IDF) systems installed, foreign technicians arrived for IDF testing and IDF operation training.
  • 09-02-2006
    Stand alone testing were conducted for waste crane.
  • 10-02-2006
    Begin stand alone testing for the Plant’s air compressor supply system.
  • 14-02-2006
    Stand-alone testing of emergency diesel generator started
  • 16-02-2006
    Waste crane stand-alone testing was successfully completed, prepare to submit test reports
  • 17-02-2006
    No. 2 steam boiler to begin the roast and boil operation.
  • 22-02-2006
    No. 1 steam boiler to begin the roast and boil operation.
  • 02-03-2006
    Completion of Loadometer system testing and the personnel education and training.
  • 03-03-2006
    Tainan County Environmental Protection Agency’s garbage trucks were in the Plant for practicing garbage dumping and correct routing
  • 03-04-2006
    YongKang City, Tainan County Cleanup Team starting to transport garbage to the plant and dumping the waste into the storage pit
  • 10-04-2006
    County Magistrate Mr. Su Huanzhi came to the construction site for project status and briefing.
  • 12-04-2006
    Working with CTCI Corporation, the emission monitoring system testing was completed on-site.
  • 14-04-2006
    Scheduled for operation starts at 11 o'clock at this day. Plant testing was conducted.
  • 11-05-2006
    Chairman of CPC along with the Director of EPA, Mr. Su Huanzhi, County Magistrate and other elected local officials at all levels attend the Plant Ignition Ceremony.
  • 12-06-2006
    Completion of single unit testing.
  • 13-07-2006
    Completion of the third control point (turbine generator was successfully integrated with the Taiwan Power Company)
  • 18-07-2006
    Completion of trial run (end-to-end testing).
  • 07-09-2006
    Completion of functional testing (waste volume test).
  • 08-09-2006
    Completion of the entire YongKang incinerator plant functional testing.
  • 11-01-2007
    Improved the building metal plate.
  • 29-03-2007
    Inspection completed (low calorific waste processing diesel volume was re-verified)
  • 03-09-2007
    1st round of acceptance test completed.
  • 12-10-2007
    Imperfection The deficiencies improvement completed (duration 30 days)
  • 24-10-2007
    Completion of 1st acceptance test improvement review.
  • 22-11-2007
    2nd round of acceptance test completed.
  • 03-12-2007
    Formal acceptance on the deficiencies improvement completion (duration 30 days)
  • 18-12-2007
    Completion of 2nd formal acceptance test improvement review.
  • 31-12-2007
    EPA approved acceptance and project completion date.
  • 18-01-2008
    CPC hand over the plant to Tainan County Government.
Location: No.166, Wangxing E. Rd., Yongkang Dist., Tainan City 710, Taiwan (R.O.C.)
Contact: TEL: 06-2319266 / FAX: 06-2316388 / Last Updates: 2024-04-29
Yong Kang, Tainan, Litter Recycling (Incineration) Plant. © ALL RIGHT RESERVED.
Suggested Browser:Google Chrome / IP Connection: - / Visit:12345678
Location: No.166, Wangxing E. Rd., Yongkang Dist., Tainan City 710, Taiwan (R.O.C.)
Contact: TEL: 06-2319266 / FAX: 06-2316388
Last Updates: 2024-04-29
Yong Kang, Tainan, Litter Recycling (Incineration) Plant. © ALL RIGHT RESERVED.
Suggested Browser:Google Chrome
IP Connection: - / Visit:12345678