::: Site Map
 
 
:::
About the Plant>>Major Events
Major Events
Date Events
26 Sept. 2003 " YongKang Waset to Energy (incineration) Plant, Tainan County," transfer to the CPC Corporation.
21 Oct. 2003~.
24 Oct. 2003
"YongKang Waset to Energy  (incineration) Plant, Tainan County" Project kickoff meeting.
12 March 2004 Plant inspection and audit was conducted by foreign technicians from a Austrian company named ENVIRGY.
08 April 2004 Completion of the first control point (the DCS control logic diagram was approved)
16 April 2004 Company registered. EPA’s equipment delivered.
16 Aug. 2004 Completion of the temporary storage facility adjacent to the Plant's construction sites and finished moving the equipments and materials to the storage facility as ordered by the Court.
31 May 2005 Siemens AG, turbine-generator's foreign service consultant arrived at site, conducted the technical guidance of the equipment installation. YongKang and training preparation were conducted.
13 June 2005 Completion of phase one.  Following the guidance of the Siemens turbine-generator’s consultant, the turbine generator was successfully installed.
08 Aug. 2005 The completion of stack painting.
11 Aug. 2005 A large garbage truck was sent by the Environmental Protection Bureau of Tainan County to conduct field measurement and contour of traffic route within the Plant.
21 Oct. 2005

The completion of the second control point (the main facility and mechanical/electrical equipment is completed and received inspection certificate for pressure vessel and refuse crane)

18 Dec. 2005 YongKang incinerator construction completed transmission of 161KV power from the Tai Power.
26 Jan. 2006

Flue gases treatment (IDF) systems installed, foreign technicians arrived for IDF testing and IDF operation training.

09 Feb. 2006 Stand alone testing were conducted for waste crane.
10 Feb. 2006 Begin stand alone testing for the Plant’s air compressor supply system.
14 Feb. 2006 Stand-alone testing of emergency diesel generator started
16 Feb. 2006 Waste crane stand-alone testing was successfully completed, prepare to submit test reports
17 Feb. 2006 No. 2 steam boiler to begin the roast and boil operation.
22 Feb. 2006 No. 1 steam boiler to begin the roast and boil operation.
02 March 2006 Completion of Loadometer system testing and the personnel education and training.
03 March 2006

Tainan County Environmental Protection Agency’s garbage trucks were in the Plant for practicing garbage dumping and correct routing

03 April 2006

YongKang City, Tainan County Cleanup Team starting to transport garbage to the plant and dumping the waste into the storage pit

10 April 2006 County Magistrate Mr. Su Huanzhi came to the construction site for project status and briefing.
12 April 2006

Working with CTCI Corporation, the emission monitoring system testing was completed on-site.

14 April 2006 Scheduled for operation starts at 11 o'clock at this day. Plant testing was conducted.
11 May 2006

Chairman of CPC along with the Director of EPA, Mr. Su Huanzhi, County Magistrate and other elected local officials at all levels attend the Plant Ignition Ceremony.

12 June 2006 Completion of single unit testing.
13 July 2006 Completion of the third control point (turbine generator was successfully integrated with the Taiwan Power Company)
18 July 2006 Completion of trial run (end-to-end testing).
07 Sept. 2006 Completion of functional testing (waste volume test).
08 Sept. 2006 Completion of the entire YongKang incinerator plant functional testing.
11 Jan. 2007 Improved the building metal plate.
29 March 2007 Inspection completed (low calorific waste processing diesel volume was re-verified)
03 Sept. 2007 1st round of acceptance test completed.
12 Oct. 2006 Imperfection The deficiencies improvement completed (duration 30 days)
24 Oct. 2007 Completion of 1st acceptance test improvement review.
22 Nov. 2007 2nd round of acceptance test completed.
03 Dec. 2007 Formal acceptance on the deficiencies improvement completion (duration 30 days)
18 Dec. 2007 Completion of 2nd formal acceptance test improvement review.
31 Dec. 2007 EPA approved acceptance and project completion date.
18 Jan. 2008 CPC hand over the plant to Tainan County Government

 

Factory Location: No.140, Ln. 1099, Zhongshan N. Rd., Yongkang City, Tainan 710, Taiwan (R.O.C.) Contact TEL :06-2319266 Fax :06-2316388
COPYRIGHT© Incineration Plant Name: Yong Kang, Tainan, litter recycling (incineration) plant ALL RIGHT RESERVED.
Suggest resolution 1024*768
By A + Web Content Accessibility Guidelines Priority