Major Events
| Date |
Events |
| 26 Sept. 2003 |
" YongKang Waset to Energy (incineration) Plant, Tainan County," transfer to the CPC Corporation. |
21 Oct. 2003~.
24 Oct. 2003 |
"YongKang Waset to Energy (incineration) Plant, Tainan County" Project kickoff meeting. |
| 12 March 2004 |
Plant inspection and audit was conducted by foreign technicians from a Austrian company named ENVIRGY. |
| 08 April 2004 |
Completion of the first control point (the DCS control logic diagram was approved) |
| 16 April 2004 |
Company registered. EPA’s equipment delivered. |
| 16 Aug. 2004 |
Completion of the temporary storage facility adjacent to the Plant's construction sites and finished moving the equipments and materials to the storage facility as ordered by the Court. |
| 31 May 2005 |
Siemens AG, turbine-generator's foreign service consultant arrived at site, conducted the technical guidance of the equipment installation. YongKang and training preparation were conducted. |
| 13 June 2005 |
Completion of phase one. Following the guidance of the Siemens turbine-generator’s consultant, the turbine generator was successfully installed. |
| 08 Aug. 2005 |
The completion of stack painting. |
| 11 Aug. 2005 |
A large garbage truck was sent by the Environmental Protection Bureau of Tainan County to conduct field measurement and contour of traffic route within the Plant. |
| 21 Oct. 2005 |
The completion of the second control point (the main facility and mechanical/electrical equipment is completed and received inspection certificate for pressure vessel and refuse crane) |
| 18 Dec. 2005 |
YongKang incinerator construction completed transmission of 161KV power from the Tai Power. |
| 26 Jan. 2006 |
Flue gases treatment (IDF) systems installed, foreign technicians arrived for IDF testing and IDF operation training. |
| 09 Feb. 2006 |
Stand alone testing were conducted for waste crane. |
| 10 Feb. 2006 |
Begin stand alone testing for the Plant’s air compressor supply system. |
| 14 Feb. 2006 |
Stand-alone testing of emergency diesel generator started |
| 16 Feb. 2006 |
Waste crane stand-alone testing was successfully completed, prepare to submit test reports |
| 17 Feb. 2006 |
No. 2 steam boiler to begin the roast and boil operation. |
| 22 Feb. 2006 |
No. 1 steam boiler to begin the roast and boil operation. |
| 02 March 2006 |
Completion of Loadometer system testing and the personnel education and training. |
| 03 March 2006 |
Tainan County Environmental Protection Agency’s garbage trucks were in the Plant for practicing garbage dumping and correct routing |
| 03 April 2006 |
YongKang City, Tainan County Cleanup Team starting to transport garbage to the plant and dumping the waste into the storage pit |
| 10 April 2006 |
County Magistrate Mr. Su Huanzhi came to the construction site for project status and briefing. |
| 12 April 2006 |
Working with CTCI Corporation, the emission monitoring system testing was completed on-site. |
| 14 April 2006 |
Scheduled for operation starts at 11 o'clock at this day. Plant testing was conducted. |
| 11 May 2006 |
Chairman of CPC along with the Director of EPA, Mr. Su Huanzhi, County Magistrate and other elected local officials at all levels attend the Plant Ignition Ceremony. |
| 12 June 2006 |
Completion of single unit testing. |
| 13 July 2006 |
Completion of the third control point (turbine generator was successfully integrated with the Taiwan Power Company) |
| 18 July 2006 |
Completion of trial run (end-to-end testing). |
| 07 Sept. 2006 |
Completion of functional testing (waste volume test). |
| 08 Sept. 2006 |
Completion of the entire YongKang incinerator plant functional testing. |
| 11 Jan. 2007 |
Improved the building metal plate. |
| 29 March 2007 |
Inspection completed (low calorific waste processing diesel volume was re-verified) |
| 03 Sept. 2007 |
1st round of acceptance test completed. |
| 12 Oct. 2006 |
Imperfection The deficiencies improvement completed (duration 30 days) |
| 24 Oct. 2007 |
Completion of 1st acceptance test improvement review. |
| 22 Nov. 2007 |
2nd round of acceptance test completed. |
| 03 Dec. 2007 |
Formal acceptance on the deficiencies improvement completion (duration 30 days) |
| 18 Dec. 2007 |
Completion of 2nd formal acceptance test improvement review. |
| 31 Dec. 2007 |
EPA approved acceptance and project completion date. |
| 18 Jan. 2008 |
CPC hand over the plant to Tainan County Government |